Posted on: December 6, 2023
PROJECT UPDATE
Kent Road and Lincoln Road Green Alley Project
December 4, 2023
Work Completed this Week
- CR Schmidt completing the installation of the porous brick pavers in the center of Lincoln Road Alley
Upcoming Work Planned Nex...
Read on...
Construction Updates
Posted on: December 6, 2023
PROJECT UPDATE
Shenstone Road Utility Improvements and Road Reconstruction Project
December 1, 2023
Work Completed this Week
- Bolder continued installing new copper residential water services on Shenstone Road- various locations
- Ame...
Read on...
Construction Updates
Posted on: November 28, 2023
PROJECT UPDATE
Kent Road and Lincoln Road Green Alley Project
November 25, 2023
Work Completed this Week
- Triggi placed Hot-Mix Asphalt for parking lot repairs and opened Kent Road Alley back to residential traffic
- Triggi framed and...
Read on...
Construction Updates
Posted on: November 22, 2023
PROJECT UPDATE
Kent Road and Lincoln Road Green Alley Project
November 18, 2023
Work Completed this Week
- CR Schmidt completing the installation of the porous brick pavers at Kent Road Alley
- Triggi removing existing pavement and exc...
Read on...
Construction Updates
Posted on: November 27, 2023
PROJECT UPDATE
Shenstone Road Utility Improvements and Road Reconstruction Project
November 25, 2023
Work Completed this Week
- Orange Crush paved the final asphalt surface layer on Shenstone Road (Delaplaine Rd to Harlem Ave)
- Bolder...
Read on...
Construction Updates
Posted on: November 20, 2023
Emergency sewer repair will be occurring at the intersection of Eastgrove Road and North Delaplaine Road tomorrow, November 21st beginning at 7:00am. Please avoid this area tomorrow morning if possible.
Construction Updates
Posted on: November 13, 2023
PROJECT UPDATE
Shenstone Road Utility Improvements and Road Reconstruction Project
November 11, 2023
Work Completed this Week
- Triggi Construction completed pouring concrete for the new curb and gutter on Shenstone Rd (Delaplaine R...
Read on...
Construction Updates
Posted on: October 30, 2023
PROJECT UPDATE
Shenstone Road Utility Improvements and Road Reconstruction Project
October 28, 2023
Work Completed this Week
- Bolder Contractors completed the new water main tie-in to the existing Riverside water system at Shenston...
Read on...
Construction Updates
Posted on: October 24, 2023
CONSTRUCTION NOTICE
Shenstone Road Utility Improvements and Road Reconstruction Project
October 23, 2023
Water Service Interruption
Please be advised that the Village’s contractor will be connecting a new section of water main at the intersection of...
Read on...
Construction Updates
Posted on: October 23, 2023
PROJECT UPDATE
Shenstone Road Utility Improvements and Road Reconstruction Project
October 21, 2023
Work Completed this Week
- Bolder Contractors completed installing residential water services from the new water main to the parkway...
Read on...
Construction Updates
Posted on: October 20, 2023
Properties located within the anticipated work area for the Shenstone water main replacement were notified of planned service disruptions by Village project engineers. Two additional service areas needed to be temporarily shut off. Attempts were made to n...
Read on...
Construction Updates
Posted on: October 19, 2023
CONSTRUCTION NOTICE
Kent Road Green Alley Reconstruction Project
October 19, 2023
The Kent Road Green Alley Reconstruction Project will begin today Thursday October 19th. During this four-week project, the alley will not be accessible. Parking for those resi...
Read on...
Construction Updates
Posted on: October 16, 2023
PROJECT UPDATE
Shenstone Road Utility Improvements and Road Reconstruction Project
October 14, 2023
Work Completed this Week
- Bolder Contractors completed installing new 36” diameter combination sewer pipe and ma...
Read on...
Construction Updates
Posted on: October 2, 2023
PROJECT UPDATE
Shenstone Road Utility Improvements and Road Reconstruction Project
September 30, 2023
Work Completed this Week
- Bolder Contractors installed new 36” diameter combination sewer pipe and manholes on Shenstone Road (Delaplaine ...
Read on...
Construction Updates
Posted on: September 19, 2023
The intersection at North Delaplaine Road and Shenstone Road will be closed at 8:00 a.m. tomorrow as part of the Shenstone Road Reconstruction Project. The closure will remain until Friday evening at 6:00 p.m. The below map notes placement of the barricad...
Read on...
Construction Updates
Posted on: September 16, 2023
PROJECT UPDATE
Shenstone Road Utility Improvements and Road Reconstruction Project
September 16, 2023
Work Completed this Week
- Bolder Contractors continued installing new water main on Shenstone Road (Delaplaine Road to Blythe Road)
- Bolder Contracto...
Read on...
Construction Updates
Posted on: September 6, 2023
Over the past few weeks, the Village provided digital and hard-copy notice regarding the Shenstone Road Utility Improvements and Reconstruction Project. The Village will continue to share periodic community updates on project progress.
Informatio...
Read on...
Construction Updates
Posted on: August 30, 2023
CONSTRUCTION NOTICE
Shenstone Road Utility Improvements and Road Reconstruction Project
August 30, 2023
It is our pleasure to inform you that the Shenstone Road Utility Improvements and Road Reconstruction Project is scheduled to begin after the upcoming Lab...
Read on...
Construction Updates