News Flash

Posted on: July 2, 2020

Selborne Road Construction Update for July 2

Selborne Road Repaving - Final Asphalt - 7-2-2020

Work Completed this Week

  • Completed adjusting manholes frames to finish grade on Selborne Road and Parkway Road
  • Completed paving the final layer (1.5 inches) of hot mix asphalt surface course on Selborne Road and Parkway Road

Upcoming Work Planned Next Two We...

Read on...

See All Construction Updates Here Construction Updates
Posted on: June 26, 2020

Selborne Road Construction Update for June 26

Selborne Road Asphalt Paving 6-26-2020

Work Completed this Week

  • Completed fine grading aggregate stone base on Selborne Road
  • Placed 3.5 inches of hot mix asphalt binder course on Selborne Road
  • Placed 1 inch of hot mix asphalt leveling binder course on Parkway Road
  • Began adjusting manhole frames to...
Read on...

See All Construction Updates Here Construction Updates
Posted on: June 19, 2020

Selborne Road Construction Update for June 19

6-12-2020 Additional Grading2Cropped

Work Completed this Week

  • Completed removal of concrete base on Selborne Road
  • Placed geogrid to stabilize soil subgrade and placed 9-inches of stone sub-base on Selborne Road from Uvedale Court to Longcommon Road
  • Began fine grading stone base on Selborne Road...
Read on...

See All Construction Updates Here Construction Updates
Posted on: June 12, 2020

Selborne Road Construction Update for June 12

6-12-2020 Additional Grading2Cropped

Work Completed this Week

  • Removed concrete base on Selborne Road from Nuttall Road through the intersection at Uvedale Court
  • Placed geogrid to stabilize the soil subgrade and placed 9-inches of stone sub-base on Selborne Road from Nuttal Road to Uvedale Cour...
Read on...

See All Construction Updates Here Construction Updates
Posted on: May 29, 2020

Selborne Road Construction Update for June 5

6-5-2020 - Geogrid and Stone

Work Completed this Week

  • Completed asphalt surface removal on Selborne Road and Parkway Road.
  • Removed concrete base on Selborne Road from Nuttall Road through the intersection at Southcote Road.
  • Placed geogrid to stabilize the soil subgrade and placed 9-inch...
Read on...

See All Construction Updates Here Construction Updates
Posted on: May 29, 2020

Selborne Road Construction Update for May 29

5-29-2020 Driveway Apron Work Resized

Work Completed this Week

  • Completed installation of exposed aggregate sidewalks throughout the job site.
  • Completed installation of concrete driveway aprons on South side of Selborne Road
  • Backfilled gap between existing pavement and new curb and gutter with st...
Read on...

See All Construction Updates Here Construction Updates
Posted on: May 22, 2020

Selborne Road Construction Update for May 22

5-22-2020 Curb and Gutter Resized for Trending

Work Completed this Week

  • Adjusted drainage structures on South side of Selborne Road
  • Completed installation of new concrete curb and gutter on South side of Selborne Road
  • Began framing for driveway aprons on South side of Selborne Road

Upcoming Work Planned N...

Read on...

See All Construction Updates Here Construction Updates
Posted on: May 15, 2020

Selborne Road Construction Update for May 15

Selborne Road Driveway Apron Resized for Trending

Work Completed this Week

  • Completed backfilling gap between new curb and existing pavement with stone on North side of Selborne Road
  • Opened all driveways for access on North side of Selborne Road
  • Saw cut pavement on South side of Selborne Road
  • Began removal of...
Read on...

See All Construction Updates Here Construction Updates
Posted on: April 24, 2020

Selborne Road Construction Update for May 8

Selborne Road Driveway Apron Resized for Trending

Work Completed this Week

  • Removed curb and gutter and driveway aprons on North side of Selborne Rd.
  • Completed reconstruction of various storm manholes on Selborne Rd.
  • Completed installation of new curb and gutter on North side of Selborne Rd
  • Completed installa...
Read on...

See All Construction Updates Here Construction Updates
Posted on: April 24, 2020

Selborne Road Construction Update for May 1

4-24-2020 Selborne Road Sidewalk Replacement

Work Completed this Week

  • Installed exposed aggregate sidewalk on both Selborne Road and Parkway Road
  • Saw cut pavement for curb removal
  • Removed curb and gutter and driveway aprons on half of Selborne Road
  • Reconstructed various storm manholes on Selborne Road

Up...

Read on...

See All Construction Updates Here Construction Updates
Posted on: April 24, 2020

Selborne Road Construction Update for April 24

4-24-2020 Selborne Road Sidewalk Replacement

Work Completed this Week

  • Set up traffic control
  • Marked out all anticipated concrete removals (subject to change)
  • Saw cut pavement for curb removal
  • Removed sidewalk
  • Began installation of exposed aggregate concrete sidewalk on Selborne

 

Upcoming Work Pla...

Read on...

See All Construction Updates Here Construction Updates