Work Completed the Past Week

  • Completed installation of storm and sanitary sewers, including outfalls.  Underground utility construction is now 100% complete.
  • Worked on concrete and asphalt restoration in Phases 4 and 5.
  • Completed topsoil, seed, and mulch in public park areas.
  • Prepped for sod in all parkway areas adjacent to homes.

Upcoming Work Planned Next Week

  • Work on concrete, asphalt and landscape restoration.  Expected completion date:  October 6, 2017.