First Division Sewer Separation Project
Progress Report
September 11, 2017
Work Completed the Past Week
- Completed sanitary sewer in Phase 4.
- Began concrete restoration in Phase 4.
- Completed 50% of storm sewer work in Phase 5.
Upcoming Work Planned Next Week
- Complete storm sewer installation in Phase 5.
- Complete concrete restoration in Phase 4.
- Complete asphalt patching of trenches in Phase 4.
- Complete landscape restoration in Phase 2, 3, and 4.