Construction Updates

Posted on: August 11, 2017

[ARCHIVED] Project Update: First Division Sewer Separation - August 11, 2017

Work Completed This Past Week

  • Completed storm sewer and sanitary sewer in Phase 3 (Scottswood - West).
  • Began storm sewer installation on Fairbank Road in Phase 4.

Upcoming Work Planned Next Week

  • Continue storm sewer and installation in Phase 4 project limits.
    • Aug 14, 2017 Intersection of Coonley and Fairbank will be closed.
  • Pavement patching and concrete restoration in Phase 2 and 3 on Bloomingbank and Scottswood - West.