Construction Updates

Posted on: August 4, 2017

[ARCHIVED] Project Update: First Division Sewer Separation - August 4, 2017

Work Completed This Past Week

  • Completed storm sewer and sanitary sewer installation on Bloomingbank (Phase 2).
  • Installed topsoil and seed in Phase 2 and Phase 3 areas. Prepared areas for sod.
  • Continued storm sewer installation in Phase 3 through Scottswood Common.

Upcoming Work Planned Next Week

  • Complete storm sewer installation in Phase 3 (Scottswood-East).
  • Begin storm sewer and outfall installation in Phase 4 project limits.
  • Begin project restoration in Phase 2 limits on Bloomingbank.