[ARCHIVED] Project Update: First Division Sewer Separation - July 14, 2017

First Division Sewer Separation Project

Progress Report

July 14, 2017

Work Completed This Past Week

  • Completed storm sewer installation in Phase 3 on Scottswood (East)
  • Completed Fairbank storm sewer installation (Phase 2)
  • Continued storm sewer installation through Scottswood Common
  • Prepared for curb installation on Fairbank, Scottswood (East) and Barrypoint

Upcoming Work Planned Next Week

  • Install curb and gutter on Fairbank, Barrypoint (flaggers will be present) and Scottswood (East)
  • Prepare for asphalt patching on Fairbank, Barrypoint and Scottswood (East)
  • Install storm sewer and sanitary sewer on Bloomingbank (Scottswood-North to Scottswood-South) - Bloomingbank and Scottswood (West) 
  • Detour will be installed starting Monday, July 17.  Access to Riverside Swim Club will be available from the west end of Bloomingbank.