[ARCHIVED] Weekly Construction Update - June 9, 2017

First Division Sewer Separation Project

Progress Report

June 9, 2017

Work Completed This Past Week

  • Contractor completed installation of new storm sewer within Phase 1.
  • Contractor began installation of new storm in Phase 2 starting with the installation of the new outfall at the Des Plaines River.
  • Jetted trenches in Phase 1 project limits.

Upcoming Work Planned Next Week

  • Contractor will begin restoration within Phase 1 limits, including concrete restoration.
  • Contractor will continue storm sewer installation within Phase 2 limits along Fairbank.