[ARCHIVED] Weekly Construction Update - May 26, 2017

First Division Sewer Separation Project

Progress Report

May 26, 2017

Work Completed This Past Week

  • Contractor continued sanitary service replacements within Phase 1 limits.
  • Contractor completed installation of sanitary manholes and connections within Phase 1.
  • Contractor continued installation of new storm sewer within Phase 1.

Upcoming Work Planned Next Week

  • Contractor will complete sanitary service adjustments and replacements within Phase 1 limits.
  • Contractor will continue installation of new storm sewer within Phase 1.
  • Contractor will perform a watermain adjustment (Thursday).