Work Completed this Week
- Completed removal of concrete base on Selborne Road
- Placed geogrid to stabilize soil subgrade and placed 9-inches of stone sub-base on Selborne Road from Uvedale Court to Longcommon Road
- Began fine grading stone base on Selborne Road from Nuttall Road to Uvedale Court
Upcoming Work Planned Next Week
- Complete fine grading stone base on Selborne Rd from Uvedale Court to Longcommon Road
- Place first layer of hot mix asphalt (3.5 inches of binder course) on Selborne Road
- Place 1” of leveling binder asphalt on Parkway Road
- Begin adjusting manhole frames to finish grade on Selborne Road