[ARCHIVED] Selborne Road Construction Update for June 19

6-12-2020 Additional Grading2Cropped

Work Completed this Week

  • Completed removal of concrete base on Selborne Road
  • Placed geogrid to stabilize soil subgrade and placed 9-inches of stone sub-base on Selborne Road from Uvedale Court to Longcommon Road
  • Began fine grading stone base on Selborne Road from Nuttall Road to Uvedale Court

Upcoming Work Planned Next Week

  • Complete fine grading stone base on Selborne Rd from Uvedale Court to Longcommon Road
  • Place first layer of hot mix asphalt (3.5 inches of binder course) on Selborne Road
  • Place 1” of leveling binder asphalt on Parkway Road
  • Begin adjusting manhole frames to finish grade on Selborne Road

See All Construction Updates Here