[ARCHIVED] Selborne Road Construction Update for May 1

4-24-2020 Selborne Road Sidewalk Replacement

Work Completed this Week

  • Installed exposed aggregate sidewalk on both Selborne Road and Parkway Road
  • Saw cut pavement for curb removal
  • Removed curb and gutter and driveway aprons on half of Selborne Road
  • Reconstructed various storm manholes on Selborne Road

Upcoming Work Planned Next Week

  • Continue with curb and gutter and driveway apron removal on North side of Selborne Road                
  • Complete installation of exposed aggregate concrete sidewalk on both Selborne Road and Parkway Road
  • Begin curb and gutter installation on North side of Selborne Road
  • Begin preparation for driveway apron installation on North of Selborne Road
  • Complete reconstructing various storm manholes on Selborne Road