Selborne Road Construction Update

4-24-2020 Selborne Road Sidewalk Replacement

Work Completed this Week

  • Set up traffic control
  • Marked out all anticipated concrete removals (subject to change)
  • Saw cut pavement for curb removal
  • Removed sidewalk
  • Began installation of exposed aggregate concrete sidewalk on Selborne

 

Upcoming Work Planned for Next Week

  • Curb and gutter removal
  • Complete installation of exposed aggregate concrete sidewalk on both Selborne and Parkway
  • Begin curb and gutter installation
  • Remove driveway aprons on half of the street
  • Begin repairs of deteriorated catch basins and manholes

See All Construction Updates Here
Facebook Twitter Email

Other News in E-Flash

Girl Playing Soccer

What's Going On Wednesday

Posted on: July 8, 2020
Thermometer-in-the-bright-sun

Cooling Center is Open

Posted on: July 8, 2020
American Flag with the Water Tower in the Background

Happy Birthday America

Posted on: July 3, 2020
Riverside Water Tower

Riverside Playgrounds are now Open!

Posted on: June 29, 2020
Golden-Retreiver-Driving-Car

Rewewal Deadline Extended

Posted on: June 29, 2020
Cicada Photo for Eflash - 6-17-2020

Cicadas have emerged in Riverside!

Posted on: June 17, 2020
Senior in Mask

June 16 Census Update

Posted on: June 16, 2020
Close up back side of new silver car parking on the asphalt road

Vehicle Stickers & Pet Tags

Posted on: June 5, 2020
Household Hazardous Waste Event

Household Hazardous Waste

Posted on: May 15, 2020