Work Completed this Week
- JE Landworks continued installing brick pavers on the east side of Riverside Road and began installing sand between the pavers.
Upcoming Work Planned Next Week
- JE Landworks will complete brick pavers and install topsoil around trees.
- D Construction will install tree grates, bike racks and planter coping and then clean up.
- Elmund Nelson will pull electrical wire and install bollards.
- D Construction is tentatively scheduled to pave the surface course of Bloomingbank Road and Riverside Road on August 3.