Construction Updates

Posted on: June 14, 2019

[ARCHIVED] Street Paving Update - June 14, 2019

Forest Avenue Sidewalk Work - 6-14-2019

Work Completed this Week

  • Finished pouring concrete sidewalks and ADA ramps on Herrick Road
  • Finished pouring concrete sidewalks, ADA ramps and curb/gutter on Forest Avenue
  • Poured concrete sidewalks, ADA ramps and curb/gutter on Barrypoint Road
  • Removed and poured concrete Metra lot driveway #2

Upcoming Work Planned for Next Week

  • Pour remaining sidewalks, curb/gutter and ADA ramps on Barrypoint Road
  • Mill existing pavement on Herrick Road, Forest Avenue and Barrypoint Road
  • Begin pavement patching and sewer structure adjustments on Herrick Road, Forest Avenue and Barrypoint Road