Work Completed this Week
- D Construction completed a sewer repair on the south side of Bloomingbank Road.
- D Construction placed and graded stone sub-base for brick pavers along the west side of Bloomingbank Road.
- Carrera Concrete framed and poured concrete curb and gutter and exposed aggregate sidewalk in the Northwest corner of Bloomingbank Road and Riverside Road.
Upcoming Work Planned Next Week
- D Construction will patch and mill the pavement on Bloomingbank Road
- JE Landworks will begin brick paver installation.