Work Completed this Week
- Completed permeable paver installation and inlaid pavement markings.
- Installed remaining concrete sidewalk and driveway pavements.
- Installed span wire for parking sign installation.
Upcoming Work Planned Next Week
- Install plantings and mulch in rain gardens.
- Complete permeable paver chip filler installation and punch list.
- Install sign foundations and posts.
- Install parking, handicap, educational, and information signs within Commuter Lot #1.
- Install remaining seed and blanket around perimeter of parking lot.
- Remove tree protection and fencing.