Work Completed during the Past Two Weeks (10/26/2018 to 11/16/2018)
- New copper water service lines were installed.
- Abandonment of the existing water main was completed.
- Drainage structure adjustments were completed.
- Installation of new curb and gutter, driveway aprons and exposed aggregate sidewalk at various locations was completed.
- Milling of existing asphalt surface was completed.
- Water main trenches and section of deteriorated asphalt base were patched.
Upcoming Work Planned (11/19/2018 to 11/26/2018)
- Paving Leveling Binder and Hot Mix Asphalt Surface Course will be completed early next week.
- Landscaping restoration at areas damaged during construction will begin next week.