Work Completed the Past Week

  • Binder asphalt installed on the 100 Block of Fairbank.
  • Drainage structure adjustments made on Fairbank and Scottswood Roads.
  • Completed all concrete work.

Upcoming Work Planned the Next Two Weeks

  • Roadway preparation for paving.
  • Finish drainage structure adjustments.
  • Begin surface asphalt paving operations on July 9. Fresh oil will be installed the morning of July 9. IN AREAS WHERE "FRESH OIL" SIGNS ARE PRESENT, DRVERS SHOULD NOT DRIVE FASTER THAN 10 MPH.  No Parking signs will be installed.
  • Begin landscaping.

2018 Capital Improvements in Riverside
Facebook Twitter Email

Other News in E-Flash

AT&T Nationwide Network Outage

Posted on: February 22, 2024
image-300x300(19)

Groveland Floodwall Project Update

Posted on: February 15, 2024
salt_300x300

Go Easy on the Pavement Salt!

Posted on: January 8, 2024
Credit Rating Graphic_resized

Village's AA+ Credit Rating Reaffirmed

Posted on: November 3, 2023
Halloween tower

Fall/Winter Brochure Available Now!

Posted on: September 25, 2023
no-soliciting-traffic-street-sign

Door to Door Solicitation List

Posted on: July 15, 2023