Work Completed the Past Week
- Roadway level binder installation completed throughout First Division.
- Milled pavement on 100 Block Fairbank Road.
- Road is closed, local traffic only.
Upcoming Work Planned the Next Two Weeks
- 100 Block of Fairbank Road Reconstruction
- Roadway subgrade undercuts and improvements on 6/28/18.
- Install binder course asphalt on 6/29/18. Residents able to utilize driveway when binder installation is completed.
- Local traffic is permitted during evening hours. Affected residents have been notified.
- Complete all outstanding concrete work.
- Removals beginning on 6/28/18.
- Installation on 6/29/18 and 6/30/18.
- Begin structure adjustments in roadway on 6/28/18 (approximately 4 days to complete all adjustments).
- Begin surface course asphalt installation on 7/3/18, starting on Fairbank.
- Asphalt driveway installation.
- No work on 7/4/18.