Construction Updates

Posted on: June 28, 2018

[ARCHIVED] Weekly Construction Update - June 28, 2018

Road-closed-signs-detour-traffic-temporary

Work Completed the Past Week

  • Roadway level binder installation completed throughout First Division.
  • Milled pavement on 100 Block Fairbank Road.
    • Road is closed, local traffic only.

Upcoming Work Planned the Next Two Weeks

  • 100 Block of Fairbank Road Reconstruction
    • Roadway subgrade undercuts and improvements on 6/28/18.
    • Install binder course asphalt on 6/29/18. Residents able to utilize driveway when binder installation is completed.
    • Local traffic is permitted during evening hours. Affected residents have been notified.
  • Complete all outstanding concrete work.
    • Removals beginning on 6/28/18.
    • Installation on 6/29/18 and 6/30/18.
  • Begin structure adjustments in roadway on 6/28/18 (approximately 4 days to complete all adjustments).
  • Begin surface course asphalt installation on 7/3/18, starting on Fairbank.
  • Asphalt driveway installation.
  • No work on 7/4/18.