Work Completed the Past Two Weeks
- Sewer structure replacements and reconstructions have been completed.
- Roadway grinding operations have been completed.
Upcoming Work Planned the Next Two Weeks
- Roadway asphalt patching.
- Impacted residents will receive notices the evening before if their driveways will be affected.
- One lane of traffic will remain open at all times to get traffic through.
- Full depth pavement removal and binder installation on Fairbank (addresses 100-180).
- Install remaining concrete work.
- Install leveling binder.