Posted on: September 25, 2017

Project Update: First Division Sewer Separation - September 25, 2017

Riverside Logo with Tower in the Background

Work Completed the Past Week

  • Completed installation of storm and sanitary sewers, including outfalls.  Underground utility construction is now 100% complete.
  • Worked on concrete and asphalt restoration in Phases 4 and 5.
  • Completed topsoil, seed, and ...
Read on...

Construction Updates Page Construction Updates
Posted on: September 18, 2017

Project Update: First Division Sewer Separation - September 15, 2017

First Division Sewer Separation

Work Completed the Past Week

  • Completed storm sewer installation in Phase 5.
  • Complete concrete restoration in Phase 4.
  • Worked on asphalt patching of trenches in Phase 4.
  • Completed 50% of storm sewer work in Phase 6.

Upcoming Work Planned Next Week

  • Complete storm...
Read on...

Construction Updates Page Construction Updates
Posted on: September 8, 2017

Weekly Construction Update - September 9, 2017

Riverside_Logo_4C

First Division Sewer Separation Project

Progress Report

September 11, 2017

Work Completed the Past Week

  • Completed sanitary sewer in Phase 4.
  • Began concrete restoration in Phase 4.
  • Completed 50% of storm sewer work in Phase 5.

Upcoming Work Planned Next Week

  • Compl...
Read on...

Visit the Construction Updates page of the website Construction Updates
Posted on: September 1, 2017

Project Update: First Division Sewer Separation - September 1, 2017

Work Completed the Past Two Weeks

  • Completed storm sewer and 90% of sanitary sewer in Phase 4.
    • Storm sewer has been installed on Fairbank, Coonley and Scottswood (East of Coonley).
  • Pavement patching and concrete restoration in Phase 2 and 3 on Bloomingbank an...
Read on...

Visit the Construction Updates page of the website Construction Updates
Posted on: August 11, 2017

Project Update: First Division Sewer Separation - August 11, 2017

Work Completed This Past Week

  • Completed storm sewer and sanitary sewer in Phase 3 (Scottswood - West).
  • Began storm sewer installation on Fairbank Road in Phase 4.

Upcoming Work Planned Next Week

  • Continue storm sewer and installation in Phase 4 project limits....
Read on...

Construction Updates Construction Updates
Posted on: August 4, 2017

Project Update: First Division Sewer Separation - August 4, 2017

Work Completed This Past Week

  • Completed storm sewer and sanitary sewer installation on Bloomingbank (Phase 2).
  • Installed topsoil and seed in Phase 2 and Phase 3 areas. Prepared areas for sod.
  • Continued storm sewer installation in Phase 3 through Scottswood C...
Read on...

Construction Updates Construction Updates
Posted on: July 28, 2017

Project Update: First Division Sewer Separation - July 28, 2017

Work Completed This Past Week

  • Installed asphalt patching on Barry Point, Fairbank, and Scottswood (East)
  • Installed storm sewer and sanitary sewer on Bloomingbank (Phase 2)

Upcoming Work Planned Next Week

  • Install storm sewer and sanitary sewer on Bloomingbank ...
Read on...

Construction Updates
Posted on: July 21, 2017

Project Update: First Division Sewer Separation - July 21, 2017

Progress Report

July 21, 2017

Work Completed This Past Week

  • Installed curb and gutter and sidewalk on Fairbank, Barrypoint and Scottswood (East)
  • Installed asphalt patching on Barrypoint and Scottswood (East)
  • Prepared for asphalt patching on Scottswood (East) a...
Read on...

Construction Updates
Posted on: July 21, 2017

Project Update: First Division Sewer Separation - July 21, 2017

Progress Report

July 21, 2017

Work Completed This Past Week

  • Installed curb and gutter and sidewalk on Fairbank, Barrypoint and Scottswood (East)
  • Installed asphalt patching on Barrypoint and Scottswood (East)
  • Prepared for asphalt patching on Scottswood (East) a...
Read on...

Construction Updates
Posted on: July 14, 2017

Project Update: First Division Sewer Separation - July 14, 2017

First Division Sewer Separation Project

Progress Report

July 14, 2017

Work Completed This Past Week

  • Completed storm sewer installation in Phase 3 on Scottswood (East)
  • Completed Fairbank storm sewer installation (Phase 2)
  • Continued storm sewer installation throu...
Read on...

Concstruction Updates Construction Updates
Posted on: July 14, 2017

New Traffic Patterns and Detours in the First Division!

First Division Sewer Separation

Work is progressing on the First Division Sewer Separation Project. Occasional road closures and detours are required. Please follow posted detours and observe posted speed limits in the construction zone at all times. Please also consider taking an alter...

Read on...

Construction Updates Construction Updates
Posted on: July 7, 2017

Project Update: First Division Sewer Separation - July 7

Work Completed This Past Week

  • Storm sewer installation continued in Phase 3 on Scottswood (East).

Upcoming Work Planned Next Week

  • Complete storm sewer installation in Phase 3 on Scottswood (East).
  • Complete Fairbank storm sewer installation. (Phase 2)
  • Begin con...
Read on...

Construction Updates Construction Updates
Posted on: June 30, 2017

New Traffic Patterns and Detours!

Construction Map 6-29-2017

Effective July 5, 2017, weather permitting, new traffic patterns and detours will be established in and around the Village of Riverside.

For the next phase of the MWRD Salt Creek Intercepting Sewer Rehabilitation Project, Kenny Construction will be working...

Read on...

Construction Detour Map Construction Updates
Posted on: June 23, 2017

Project Update: First Division Sewer Separation - June 23, 2017

First Division Sewer Separation Project - Progress Report

June 23, 2017

Work Completed This Past Week

  • Storm sewer installation continued along Fairbank and Barrypoint in Phase 2 project limits.
  • Barrypoint Detour was installed.
  • Asphalt patching restora...
Read on...

Construction Updates
Posted on: June 16, 2017

Project Update: First Division Sewer Separation

Entire Construction Area:

  • All trees within construction limits have been pruned as needed.
  • Tree protection has been established.
  • Perimeter erosion barriers have been installed at the outfall locations.

Phase 1:  

  • All sanitary service and water main ad...
Read on...

Construction Updates
Posted on: June 9, 2017

Weekly Construction Update - June 9, 2017

First Division Sewer Separation Project

Progress Report

June 9, 2017

Work Completed This Past Week

  • Contractor completed installation of new storm sewer within Phase 1.
  • Contractor began installation of new storm in Phase 2 starting with the installation of the ...
Read on...

Construction Updates
Posted on: May 19, 2017

1st Division Sewer Separation Project Update

First Division Sewer Separation Project

Progress Report

May 19, 2017

Work Completed This Past Week

  • Contractor continued sanitary service replacements within Phase 1 limits.
  • Contractor began installation of new sanitary manholes and new storm sewer line within ...
Read on...

Construction Updates
Posted on: May 12, 2017

Weekly Construction Update - May 12

Road-closed-signs-detour-traffic

First Division Sewer Separation Project - Progress Report - May 12, 2017

Work Completed This Week

  • Contractor completed installation of tree protection fencing.
  • Contractor began installations of sanitary service adjustments and replacements ...
Read on...

Construction Updates
Posted on: May 10, 2017

Construction Update - May 10

Road-closed-signs-detour-traffic

Pavement striping on Quincy and Longcommon will be installed May 10th.  Please allow additional time and utilize caution while driving in the area and obey any posted no parking or temporary detours signs and any flaggers.  The stamped a...

Read on...

Construction Updates
Posted on: May 5, 2017

Weekly Construction Update - May 5

First Division Sewer Separation Project

Progress Report

May 5, 2017

Work Completed This Past Week

  • Contractor installed perimeter erosion barrier along four outfall work areas.
  • Contractor removed trees, canopy pruned trees, and root pruned trees.
  • Contractor inst...
Read on...

Construction Updates