News Flash

Posted on: May 17, 2019

Construction Update - May 17, 2019

Herrick Road Repaving Photo - 4-26-2019

Work Completed this Week

  • There was no work on this project during the past week.

Upcoming Work Planned for Next Week

  • Removing curb & gutter on Herrick Road.
  • Removing existing ADA ramps at Herrick Road & Cowley Road.
Read on...

View All Updates Here Construction Updates
Posted on: May 10, 2019

Construction Update - May 10, 2019

5-10-2019 Paver Completion

Work Completed this Week

  • Completed permeable paver installation and inlaid pavement markings.
  • Installed remaining concrete sidewalk and driveway pavements.
  • Installed span wire for parking sign installation.

Upcoming Work Planned Next Week

  • Install plantings and...
Read on...

View All Updates Here Construction Updates
Posted on: May 9, 2019

Construction Notice

Metra Pedestrian Access Improvements Snip for Trending

The Metra Pedestrian Access Improvement Project is scheduled to begin on Monday, May 13, 2019.  The project consists of reconstructing the intersection at Riverside Road and Bloomingbank Road, installing brick paver pedestrian walkways, bicycle r...

Read on...

Learn more about the project here. Construction Updates
Posted on: May 3, 2019

Construction Update - May 3, 2019

5-3-2019 - Lot 1 Pavers 1

Work Completed this Week

  • Continued brick paver installation.
  • Installed brick paver parking striping.
  • Removed curb and sidewalk in preparation for concrete installation.

Upcoming Work Planned Next Week

  • Begin installing plantings in rain garden (weather permitti...
Read on...

View All Updates Here Construction Updates
Posted on: April 26, 2019

Construction Update - April 26, 2019

4-23-2019 - Pavers 6 Resized for Trending

Work Completed this Week

  • Installed small aggregate to level for brick paver installation.
  • Began brick paver installation.

Upcoming Work Planned Next Week

  • Begin installing plantings in rain garden.
  • Continue brick paver installation.
  • Install remaining concrete cu...
Read on...

View All Updates Here Construction Updates
Posted on: April 26, 2019

Street Paving Update - April 26, 2019

Herrick Road Repaving Photo - 4-26-2019

Work Completed this Week

  • Removed frames on all drainage structures to be adjusted or reconstructed on Herrick Road, Forest Avenue and Barrypoint Road.
  • Installed new catch basins and a sanitary manhole on Herrick Road.

Upcoming Work Planned Next Week

  • Sawcuttin...
Read on...

View All Updates Here Construction Updates
Posted on: April 23, 2019

Street Paving Update - April 19, 2019

Herrick Road Repaving Project Week 1 - 4-23-2019

Weekly Report #1 - April 19, 2019

Work Completed this Week

  • Mobilized to Herrick Road.
  • Investigated all existing drainage structures.
  • Sawcut removal limits for drainage structure replacement on Herrick Road and Forest Avenue.

Upcoming Work Planned Next...

Read on...

View All Updates Here Construction Updates
Posted on: April 22, 2019

Construction Update - April 19, 2019

Commuter Lot 1 Green Parking Lot April 16

Work Completed this Week

  • Installed final course of aggregate prior to brick paver installation with fine grading and roller compaction.
  • Installed remaining curb and gutter and concrete edge restraint within parking lot.
  • Removed sidewalk along north Bloomingb...
Read on...

View All Updates Here Construction Updates
Posted on: April 12, 2019

Construction Update - April 12, 2019

Rain_Garden_Parking_Lot_1_in_Progress

Work Completed this Week

  • Installed coarse aggregate subgrade in parking lot.
  • Installed remaining storm sewer and observation wells.
  • Final grade in Rain Garden 1 and Rain Garden 2.
  • Installed seed and blanket along the rain garden.
  • Began concrete curb installati...
Read on...

View All Updates Here Construction Updates
Posted on: April 5, 2019

Construction Update - April 5, 2019

4-5-2019 - Lot 1 Photo 3 Resized for Trending

Work Completed this Week

  • Installed electrical conduit, bollard foundations and light pole foundations.
  • Installed wire span poles and foundations.
  • Installed storm sewer and open manhole connections to the rain garden.
  • Removed existing drainage structures.

Upcom...

Read on...

View All Updates Here Construction Updates
Posted on: April 3, 2019

2019 Road Construction

Road-closed-signs-detour-traffic-temporary

The Village's 2019 street resurfacing projects are scheduled to begin on Herrick Road on April 15.   Forest Avenue and Barrypoint Road will also be resurfaced.  IDOT has awarded the resurfacing contract to Lindahl Brothers of Bensenville...

Read on...

View All Updates Here Construction Updates
Posted on: March 29, 2019

Construction Update

Truck-Working-Commuter-Lot-1-3-27-2019

Work Completed this Week

  • Completed removals of parking lot existing subbase down to final subgrade.
  • Completed removals and grading for subgrade elevations for Rain Garden 1 and Rain Garden 2.

Upcoming Work Planned Next Week

  • Remove existing parking lot drainag...
Read on...

View All Updates Here Construction Updates
Posted on: March 22, 2019

Construction Update

3-22-2019 Lot 1 Photo

Work Completed the Past Week

  • Work began on March 16, 2019.
  • Installed temporary lighting in Riverside Swim Club parking lot.
  • Installed temporary striping/numbering in Riverside Swim Club parking lot and additional train station parking.
  • Installed tree protecti...
Read on...

View All Updates Here Construction Updates