Construction Updates

Posted on: September 8, 2017

Weekly Construction Update - September 9, 2017

Riverside_Logo_4C

First Division Sewer Separation Project

Progress Report

September 11, 2017

Work Completed the Past Week

  • Completed sanitary sewer in Phase 4.
  • Began concrete restoration in Phase 4.
  • Completed 50% of storm sewer work in Phase 5.

Upcoming Work Planned Next Week

  • Complete storm sewer installation in Phase 5.
  • Complete concrete restoration in Phase 4.
  • Complete asphalt patching of trenches in Phase 4.
  • Complete landscape restoration in Phase 2, 3, and 4.