Project Update: First Division Sewer Separation - September 1, 2017

Work Completed the Past Two Weeks

  • Completed storm sewer and 90% of sanitary sewer in Phase 4.
    • Storm sewer has been installed on Fairbank, Coonley and Scottswood (East of Coonley).
  • Pavement patching and concrete restoration in Phase 2 and 3 on Bloomingbank and Scottswood - West.
    • Driveway aprons and curb have been poured on Bloomingbank and Scottswood.
    • Topsoil and seeding on Bloomingbank and Scottswood.

 

Upcoming Work Planned Next Week

  • Construction will start on Phase 5 on September 5, 2017.
  • Sanitary sewer work on Phase 4.
    • Intersection of Coonley/Fairbank will be closed on Tuesday, September 5, 2017 due to sanitary sewer work.
    • 280 to 268 Fairbank Rd.
  • Pavement patching and concrete restoration will start on Phase 4.
    • Fairbank Rd and Scottswood Rd